Contract Name: King's College School, Wimbledon
Contract Value: £2 million
Contract Period: 31 weeks
Architect: NVB
Client: The Corporation of Kings College School

Rydon was selected to design and build an extension to the three-storey science block, providing a range of laboratory and teaching facilities for King’s College School in Wimbledon.

The project involved the construction of a 676m² extension and the refurbishment of an existing 298m² to create a totally new and enhanced science facility which has benefited some 1,200 pupils from both the senior and junior sections of the school.

During the construction period, the main school remained fully operational throughout, with the works fitting around school schedule; therefore, great care and close liaison with the teaching staff was essential to ensure the minimum of disruption.

Additionally, the scheme included the installation of wind generators to contribute towards making the building very energy efficient.